On-Time Guarantee: On time, or 5% back
Andes Construction Services LLC, doing business as Awesome Group Construction.
- The promise. We deliver your project through the final checklist by the completion date on your signed schedule, or we take 5% off. It applies to every project we build.
- When it counts as delivered. On the day the final checklist is signed by you and by us. The time you take to review and sign the final checklist does not count against us.
- What the 5% is calculated on. The original contract price. If a change order affects the entire contract, the 5% is calculated on the total including that change order. A change order for a specific additional item is not covered by this guarantee.
- How it is applied. Automatically. Your last payment is 10% of the contract total; if we miss the date, it drops to 5%. Nothing to claim, no cap.
- Which date applies. The completion date on the most recent schedule you have signed, plus any days added for the reasons below.
- Change orders. Every change order comes with a new schedule that you sign.
- Your selections. If a selection is made late, or you choose something that will take longer to arrive, we issue a new schedule for you to sign.
- Permits and inspections. The schedule includes one week for permits. If the city takes longer than that, or delays an inspection through no fault of ours, the extra days are added to the schedule. If we fail an inspection, those days are not added.
- Rain. Every day rain prevents work is added to the schedule. We notify you each time.
- Hidden conditions. If we uncover a hidden condition that needs an engineer, we tell you and the clock stops until a new schedule is signed.
- Materials. If a material will arrive later than expected, we offer you alternatives that are in stock. If you prefer to wait for the original, we issue a new schedule for you to sign. If the delay is the supplier's fault, the days are added to the schedule.
- Events beyond anyone's control. Natural disasters and government orders extend the schedule by the time they cost.
- How you track it. Every schedule movement and its cause is logged in the app, visible to you the day it happens.
- Your contract. These terms are part of your construction contract.